Cost Breakdown
Name/Model: 50-Ton Pile Driver Engineering Mech
Technology: Clan
Tonnage: 50
Configuration: Biped IndustrialMech
========================================================================================================================
Structural Cost
------------------------------------------------------------------------------------------------------------------------
Armor (Ferro-Fibrous): (163 pts) 8.5 x 20,000 170,000.00
Internal Structure (Industrial): 50 x 300 x 1 (+) 15,000.00 = 185,000.00
Myomer (Standard): 50 x 2,000 (+) 100,000.00 = 285,000.00
Engine (Fusion): (5,000 x 150 x 50) / 75 (+) 500,000.00 = 785,000.00
Gyro (Standard): 2.0 x 300,000 (+) 600,000.00 = 1,385,000.00
Cockpit (Industrial): 100,000 (+) 100,000.00 = 1,485,000.00
Life Support: 50,000 (+) 50,000.00 = 1,535,000.00
Sensors: 50 x 2,000 (+) 100,000.00 = 1,635,000.00
Heat Sinks (Single): 6 x 2,000 (+) 12,000.00 = 1,647,000.00
Arm Actuators: 50 x ((100 x 2) + (50 x 1) + (80 x 0)) (+) 12,500.00 = 1,659,500.00
Leg Actuators: 50 x ((150 x 2) + (80 x 2) + (120 x 2)) (+) 35,000.00 = 1,694,500.00
------------------------------------------------------------------------------------------------------------------------
Total Structural Cost: 1,694,500.00
========================================================================================================================
Weapons and Equipment Cost
------------------------------------------------------------------------------------------------------------------------
CASE 2 x 50,000 100,000.00
Heavy-Duty Pile Driver 100,000 (+) 100,000.00 = 200,000.00
Lift Hoist 50,000 (+) 50,000.00 = 250,000.00
Machine Gun 5,000 (+) 5,000.00 = 255,000.00
Machine Gun 5,000 (+) 5,000.00 = 260,000.00
Machine Gun 5,000 (+) 5,000.00 = 265,000.00
Machine Gun 5,000 (+) 5,000.00 = 270,000.00
Machine Gun (Ammo 100) [Empty Bin] 0 (+) 0.00 = 270,000.00
Machine Gun (Ammo 100) [Empty Bin] 0 (+) 0.00 = 270,000.00
------------------------------------------------------------------------------------------------------------------------
Total Weapons and Equipment Cost 270,000.00
========================================================================================================================
IndustrialMech Cost
------------------------------------------------------------------------------------------------------------------------
Structural Cost: 1,694,500.00
Weapons and Equipment Cost: (+) 270,000.00 = 1,964,500.00
IndustrialMech Cost Multiplier: 1 + (50 / 400) (*) 1.13 = 2,210,062.50
------------------------------------------------------------------------------------------------------------------------
Final IndustrialMech Cost 2,210,063.00
|