Cost Breakdown
Name/Model: Patron PTN-2M PatrolMech
Technology: Inner Sphere
Tonnage: 15
Configuration: Biped IndustrialMech
==============================================================================================================================
Structural Cost
------------------------------------------------------------------------------------------------------------------------------
Armor (Heavy Industrial): (32 pts) 2.0 x 10,000 20,000.00
Internal Structure (Industrial): 15 x 300 x 1 (+) 4,500.00 = 24,500.00
Myomer (Standard): 15 x 2,000 (+) 30,000.00 = 54,500.00
Engine (Fuel Cell): (3,500 x 30 x 15) / 75 (+) 21,000.00 = 75,500.00
Gyro (Standard): 1.0 x 300,000 (+) 300,000.00 = 375,500.00
Cockpit (Industrial w/ Adv. FCS): 200,000 (+) 200,000.00 = 575,500.00
Life Support: 50,000 (+) 50,000.00 = 625,500.00
Sensors: 15 x 2,000 (+) 30,000.00 = 655,500.00
Heat Sinks (Single): 1 x 2,000 (+) 2,000.00 = 657,500.00
Arm Actuators: 15 x ((100 x 2) + (50 x 2) + (80 x 2)) (+) 6,900.00 = 664,400.00
Leg Actuators: 15 x ((150 x 2) + (80 x 2) + (120 x 2)) (+) 10,500.00 = 674,900.00
------------------------------------------------------------------------------------------------------------------------------
Total Structural Cost: 674,900.00
==============================================================================================================================
Weapons and Equipment Cost
------------------------------------------------------------------------------------------------------------------------------
Light Machine Gun 5,000 5,000.00
Light Machine Gun 5,000 (+) 5,000.00 = 10,000.00
Light Machine Gun 5,000 (+) 5,000.00 = 15,000.00
Light Machine Gun 5,000 (+) 5,000.00 = 20,000.00
Light Machine Gun (Ammo 100) [Empty Bin] 0 (+) 0.00 = 20,000.00
Light Machine Gun (Ammo 100) [Empty Bin] 0 (+) 0.00 = 20,000.00
Rocket Launcher 10 15,000 (+) 15,000.00 = 35,000.00
Rocket Launcher 10 15,000 (+) 15,000.00 = 50,000.00
Rocket Launcher 10 15,000 (+) 15,000.00 = 65,000.00
------------------------------------------------------------------------------------------------------------------------------
Total Weapons and Equipment Cost 65,000.00
==============================================================================================================================
IndustrialMech Cost
------------------------------------------------------------------------------------------------------------------------------
Structural Cost: 674,900.00
Weapons and Equipment Cost: (+) 65,000.00 = 739,900.00
IndustrialMech Cost Multiplier: 1 + (15 / 400) (*) 1.04 = 767,646.25
------------------------------------------------------------------------------------------------------------------------------
Final IndustrialMech Cost 767,646.00
|