Cost Breakdown
Name/Model: Heavy LRM Carrier J-1
Technology: Inner Sphere
Tonnage: 80
Configuration: Tracked Combat Vehicle
===============================================================================================================
Structural Cost
---------------------------------------------------------------------------------------------------------------
Armor (Heavy Ferro-Fibrous) (99 pts) 5.0 x 25,000 125,000.00
Internal Structure (Standard) 8.0 x 10,000 (+) 80,000.00 = 205,000.00
Control Components 4 x 10,000 (+) 40,000.00 = 245,000.00
Engine (Fuel Cell) (3,500 x 160 x 80) / 75 (+) 597,333.33 = 842,333.33
Heat Sinks (Single) 1 x 2,000 (+) 2,000.00 = 844,333.33
Turret 4.5 x 5,000 (+) 22,500.00 = 866,833.33
---------------------------------------------------------------------------------------------------------------
Total Structural Cost 866,833.33
===============================================================================================================
Weapons and Equipment Cost
---------------------------------------------------------------------------------------------------------------
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 0.00
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 (+) 0.00 = 0.00
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 (+) 0.00 = 0.00
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 (+) 0.00 = 0.00
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 (+) 0.00 = 0.00
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 (+) 0.00 = 0.00
LRM 20 (Ammo 6) [Semi-Guided] [Empty Bin] 0 (+) 0.00 = 0.00
LRM 20 w/ Artemis IV FCS 250,000 + 100,000 (+) 350,000.00 = 350,000.00
LRM 20 w/ Artemis IV FCS 250,000 + 100,000 (+) 350,000.00 = 700,000.00
LRM 20 w/ Artemis IV FCS 250,000 + 100,000 (+) 350,000.00 = 1,050,000.00
LRM 20 w/ Artemis IV FCS 250,000 + 100,000 (+) 350,000.00 = 1,400,000.00
---------------------------------------------------------------------------------------------------------------
Total Weapons and Equipment Cost 1,400,000.00
===============================================================================================================
Combat Vehicle Cost
---------------------------------------------------------------------------------------------------------------
Structural Cost 866,833.33
Weapons and Equipment Cost (+) 1,400,000.00 = 2,266,833.33
Combat Vehicle Cost Multiplier 1 + (80 / 100) (*) 1.8 = 4,080,300.00
---------------------------------------------------------------------------------------------------------------
Final Combat Vehicle Cost 4,080,300.00
|