Cost Breakdown
Name/Model: Cheetah B
Technology: Clan
Tonnage: 20
Configuration: Biped BattleMech
========================================================================================================================
Structural Cost
------------------------------------------------------------------------------------------------------------------------
Armor (Ferro-Fibrous): (67 pts) 3.5 x 20,000 70,000.00
Internal Structure (Endo Steel): 20 x 1,600 x 1 (+) 32,000.00 = 102,000.00
Myomer (Standard): 20 x 2,000 (+) 40,000.00 = 142,000.00
Engine (XL): (20,000 x 220 x 20) / 75 (+) 1,173,333.33 = 1,315,333.33
Gyro (Standard): 3.0 x 300,000 (+) 900,000.00 = 2,215,333.33
Cockpit (Standard): 200,000 (+) 200,000.00 = 2,415,333.33
Life Support: 50,000 (+) 50,000.00 = 2,465,333.33
Sensors: 20 x 2,000 (+) 40,000.00 = 2,505,333.33
Heat Sinks (Double): 10 x 6,000 (+) 60,000.00 = 2,565,333.33
Arm Actuators: 20 x ((100 x 2) + (50 x 2) + (80 x 2)) (+) 9,200.00 = 2,574,533.33
Leg Actuators: 20 x ((150 x 2) + (80 x 2) + (120 x 2)) (+) 14,000.00 = 2,588,533.33
------------------------------------------------------------------------------------------------------------------------
Total Structural Cost: 2,588,533.33
========================================================================================================================
Weapons and Equipment Cost
------------------------------------------------------------------------------------------------------------------------
CASE 2 x 50,000 100,000.00
ER Medium Laser 80,000 (+) 80,000.00 = 180,000.00
ER Small Laser 11,250 (+) 11,250.00 = 191,250.00
Machine Gun 5,000 (+) 5,000.00 = 196,250.00
Machine Gun 5,000 (+) 5,000.00 = 201,250.00
Machine Gun 5,000 (+) 5,000.00 = 206,250.00
Machine Gun 5,000 (+) 5,000.00 = 211,250.00
Machine Gun 5,000 (+) 5,000.00 = 216,250.00
Machine Gun 5,000 (+) 5,000.00 = 221,250.00
Machine Gun 5,000 (+) 5,000.00 = 226,250.00
Machine Gun 5,000 (+) 5,000.00 = 231,250.00
Machine Gun (Ammo 100) [Empty Bin] 0 (+) 0.00 = 231,250.00
Machine Gun (Ammo 100) [Empty Bin] 0 (+) 0.00 = 231,250.00
------------------------------------------------------------------------------------------------------------------------
Total Weapons and Equipment Cost 231,250.00
========================================================================================================================
BattleMech Cost
------------------------------------------------------------------------------------------------------------------------
Structural Cost: 2,588,533.33
Weapons and Equipment Cost: (+) 231,250.00 = 2,819,783.33
BattleMech Cost Multiplier: 1 + (20 / 100) (*) 1.20 = 3,383,740.00
------------------------------------------------------------------------------------------------------------------------
Final BattleMech Cost 3,383,740.00
|